In our company we have a lot of customer related projects that are not only smaller in size then internal projects, but also requires us to report the amount of hours we have spent on a project.
What I would like to see is that the percent can be based on time spent / total estimated time. This is what we need:
  1. Besides the current start date/end date chart we need a time estimation feature. Example; a project is due in three weeks, but in only requires 10 hours of development.
  2. Add a time spent feature where our developers can add the time they have spent on a project. The percent calculation should then update based on time spent / estimated time. Example; The project is estimated to take 10 hours and 2 hours have been spent so far. The percentage should show that 20% of the project is done without the need to calculate it manually.
  3. A nice way to show the hours spent in the chart.