Allow a task or milestone to be marked as "locked." so that it doesn't automatically move when other dependent tasks move.
complete
T
Tim Macchi
Merged in a post:
Fixed dates milestones
Liqun He
Allow milestones to be fixed in place.
K
Kelsey Ingerto
complete
This is available in Gantt view. Project managers can go to Menu > Project Settings to lock or unlock all milestones in a project!
K
Kelsey Ingerto
Merged in a post:
Add ability to lock a group/tasks
G
Gilles Plot
I would like to prevent myself or co-workers from moving a group/task by accident.
K
Kelsey Ingerto
Merged in a post:
Allow the user to set a fixed date for a milestone that will not move
Brad Sileo
This way I can set a fixed date for a critical milestone and see it turn the dependencies red when the project changes and we may miss this milestone.
K
Kelsey Ingerto
Merged in a post:
enable fixed end or start dates
A
ASingh
so that tasks don't moved based on delays in other areas. some tasks must be completed/start by a certain date regardless