Dependencies - more options
under review
T
Tim Macchi
Merged in a post:
Addition of Start to start (SS) linkage and task indent and outdent feature
PMO
I have below two requirement
a) can we add Start to start (SS) linkage between task
b) can we have indent and outdent feature for task. This will also solve of requirement of subtask. If anyone wants to create subtask, he/she can indent subtasks in his own task.
If these are available then it will be really great orelse i requirement to take these as development plan for next version release as it is beneficial for longterm
T
Tim Macchi
Merged in a post:
Lack of dependencies
Tomas Mureika
There is an obvious lack of dependencies (SF,FF, SS, etc.,) as well as the lag for successor (+/- days to next task)
T
Tim Macchi
Merged in a post:
Task Relationships
Chris Halliday
It would be great to allow for other types of task relationships such as Start-Start and Finish-Finish. Multiple times I have had to create unnecessary milestones in my schedules to tie-off overlapping activities.
T
Tim Macchi
Merged in a post:
More Dependency Types
M
Miguel Chaves
T
Tim Macchi
Merged in a post:
Add more dependency options, start to start, start plus x to start (this is very common), end to end
D
Djames9847
T
Tim Macchi
Merged in a post:
More dependency types
Jon Hurrell
There are usually 4 types and we only seem to have access to 1 which limits the use of Team Gantt quite considerably for more complex schedules.
K
Kelsey Ingerto
under review
K
Kelsey Ingerto
Merged in a post:
Dependent tasks on same date
A
Alex Guez
When task 1 (T1) is issue on a day D and task 2 is dependent on T1 , the line joining T1 and T2 is read when T1 finish date and T2 beginning date are the same...
When linked, it is quite usual to begin a task the date when prior task is finished.
K
Kelsey Ingerto
Merged in a post:
Allow multiple dependencies
F
Florian Dierickx
Allow multiple outgoing dependencies to multiple other tasks (would be very handy if one task is a preparation that feeds into multiple other tasks. In my case: preparation for presentation/article feeds into multiple events, conferences and other articles)
K
Kelsey Ingerto
Merged in a post:
dependencies
A
Aurélien Boulben
Can we fix a dependencies in time. I mean I would start the task 2 only 6 weeks after the end of the task 1. If the task 1 finished sooner or later, I want the task 2 start still 6 weeks after.
Thanks